Construction works in the frame of EU funded Project

On May 22, monitoring group of Shen NGO together with heads of Areguni and Pambak Cooperatives, Village mayors, “Vardenis” Water Users Association’s Specialist and representatives of contractor conducted an inspection of wells drilled and cleaned in 2017. The commitee confirmed that the water capacity in the wells was not sufficient for the irrigation.

The committee members made a monitoring visit to the communities of Geghamasar, Pambak and Areguni. It was found out that the construction of a 1,300-square-meter greenhouse in Geghamasar is under way, the small greenhouse of Pambak is ready for exploitation and the first sprouts of the plants are already visible in Areguni.